Wednesday, 14 November 2018

More bricks, a temporary front door and a bath frame


The bricklayers have been making good daily progress - it was raining today and they still showed up and managed to do some work.

There is also still timber work going on inside, finishing up loose ends before plasterboard apparently starts next week.

By the way, despite appearances so far, the whole house is not going to be face brick!












Sunday, 11 November 2018

Tuesday, 6 November 2018

Dribs and drabs

Work is ongoing...roof tiles have been installed onto single story parts (garage and rear). Plumbing and aircon ducting is also being installed. Bricks have been delivered










Tuesday, 23 October 2018

Framing officially complete

Framing is officially complete, and the top story roof has gone on, as well as a lot of the plumbing.








 

Monday, 8 October 2018

Windows and almost completion of framing

There are no bits of framing left outside, so guess it has all been installed. Windows have gone in as well. No idea what the pile of sand out front is for though.







Tuesday, 2 October 2018

Second story framing

So we got back from a week's holiday to find that the second story frame was well underway...












 

Builders closed for holidays

Officially the builders are closed for their holidays, but apparently some of the subcontractors will still be working, specifically the out...