Monday 30 April 2018

House ready for demolition

So we are ready to hand the house over to the demolishers.

We have moved out, and sold a lot of the fittings (windows, doors, central heating, pergola, water heaters, pool pumps, pool heating, kitchen cupboards, gates, plumbing etc etc etc.) - provided a nice little cash boost.

We then had to wait for the gas and electricity services to be completely removed by the relevant utilities companies, which is a waiting game - they won't provide any dates or timelines, other than "up to 30 working days". They won't even tell you when they have done the job, you have to keep checking.

We also had to provide the temporary fencing ourselves.

The stuff with safety tape around it is what we are keeping, ie the demolishers won't touch it (hopefully!)

















Sunday 1 April 2018

The beginning

So we have decided to demolish our house and build a new one on the same site.

To anyone wondering, yes we do have masochistic tendencies.

But after a long process of house hunting, talking to builders about renovating the existing house, and other builders about building a new house, all roads have led to this option as offering the best result at the best value.

So what are we building???

You may just have to wait and see 😁

Although one thing I can promise is that it won't look anything like this.....







Builders closed for holidays

Officially the builders are closed for their holidays, but apparently some of the subcontractors will still be working, specifically the out...